Co-Op Cardiff

Description

M&P are currently installing the SFS and Render package at Archbishop McGrath High School in Bridgend. There are a variety of interfaces with other works such as the roof cladding, rainscreen wall panelling and brickwork areas. The works include hi-spec compound lintels to the windows and inclined windows to suit the cladding of the sports hall area. The project is currently ahead of programme with the aim of completion in late November.

M&P Scope of works

SFS External Framing and associated works plus Alsecco Render.

Project details

  • Main Contractor Tilbury Douglas
  • Building Type New Co-op Superstore
  • M&P Value £120,000
  • Start and completion date 1993

Social Media Share