Description
M&P are currently installing the SFS and Render package at Archbishop McGrath High School in Bridgend. There are a variety of interfaces with other works such as the roof cladding, rainscreen wall panelling and brickwork areas. The works include hi-spec compound lintels to the windows and inclined windows to suit the cladding of the sports hall area. The project is currently ahead of programme with the aim of completion in late November.
M&P Scope of works
SFS External Framing and associated works plus Alsecco Render.
Project details
-
Main Contractor Laing O’Rourke
-
Architect Powell Dobson
-
Building Type Hospital
-
M&P Value £850,000
-
Start and completion date Feb 2013 – Oct 2013