Description
M&P are currently installing the SFS, Cement Board, Insulation, brick tie channels and vapour control barrier packages at the Gateways to the Valleys Secondary School in Bridgend for Leadbitter Construction. There are a variety of interfaces with other works such as the roof cladding, curtain walling and brickwork . The project is of a fast track nature and consists of six separate phases within the overall programme.
M&P Scope of works
SFS External Framing , Cement Particle Board, Insulation, Bricktie Channels, Vapour Control Barrier, Weber Insulated and Rainscreen Render.
Project details
-
Main Contractor Leadbitter
-
Architect Scott Brownrigg
-
Building Type Secondary School
-
M&P Value £1,100,000
-
Start and completion date Feb 2012 – March 2013