Description
M&P were specifically brought in by Maslen Ltd in a partnering relationship due to our experience of delivering detailed Projects both on programme and within budget.
The fast track nature of the project also called for M&P to work with separate teams of operatives on a day and night shift basis to ensure the project completion date was achieved.
M&P also erected various suspended ceilings on this project for Diespeker Interiors.
M&P Scope of works
Metal Stud Partitions, Dry lining, MF Ceilings, Feature Bulkheads and style trims.
Project details
-
Main Contractor Amec
-
Building Type New World Trade Centre
-
M&P Value £100,000
-
Start and completion date 1993